Change a project's budget, VAT or currency
Update the total budget, currency, VAT rate, FF&E share and whether product prices include VAT.
The budget drives the spend figures on the Projects page and the overview. VAT settings decide how invoices treat prices.
Before you start
- You need permission to edit projects.
Steps
- Open the project and click Settings, then Financial.
- Under Budget & currency, change any of:
- Total budget
- Currency
- VAT / tax rate
- FF&E (the percentage of the budget for products)
- Product prices include VAT
- Click Save changes.
What happens next
- Spend against budget on Projects and the overview uses the new budget.
- If you changed the currency, a bar asks you to reload. Click Reload now so prices on Procurement and Finance show in the new currency.
- With Product prices include VAT on, invoices take the VAT out of each price. With it off, invoices add VAT on top.
Good to know
- Use numbers only. Negative numbers are not accepted, and VAT / tax rate and FF&E can't be more than 100.
- Leave a field blank to clear it.
- New projects take their VAT and FF&E figures from your studio defaults.